02
Signing of Contract
合同簽訂
03
Project Confirmation(Project Engineer Tracing)
項(xiàng)目確定(項(xiàng)目工程師全程跟蹤)
04
Reviewing Technology Scheme
(Customer Confirmation)
技術(shù)方案評審(客戶確認(rèn)會(huì)簽)
05
CAD Design
CAD設(shè)計(jì)
06
Purchasing Main Material
主體材料訂購
07
Purchasing Mould Base
模架訂購
09
Weekly Process Feedback
每周生產(chǎn)進(jìn)度反饋
10
Intermediate Procedure Inspection
中間工序檢測
11
Parting and Clamping
分型合模
12
Mould Testing and Updating
模具試模修正
13
Proving Product Samples
提供產(chǎn)品稿樣
14
Discussing with Customers on Product Refine Scheme
與客戶共同檢討產(chǎn)品修正方案
15
Accepting Certificate of Compliance Provided by Customers
客戶提供產(chǎn)品合格確認(rèn)書
16
Painting and Shipment
模具噴漆發(fā)運(yùn)
17
After-sales Service in Customer’s Factories
售后人員到達(dá)客戶指定廠家
18
Testing Production Line
生產(chǎn)線調(diào)試
19
Filling Customer Feedback
客戶信息反饋歸檔